Asked By LemonWithMin
24-May-08 11:12 AM
Hi

In MS Project, to change the scheduling options for a project, we go to
Tools -->Options -->Schedule --> Scheduling option for Project Name,

and then we change the settings as we want. For example, to present works in
days instead of hours, we set Days in [Work is entered in:] dropdown list.
But how can we do that in Project Server?

We use mandays, and we need the views in project center and project details
to show work in days instead of hours, can you help me please?

Thank you

You can change the reporting units in the timesheet from hours to days and

Asked By pconroyATtheprojectserverguruDOTcoDOTnz
24-May-08 05:04 PM
You can change the reporting units in the timesheet from hours to days and
then import the timesheet data into task updates

server settings>Timesheet Settings & Defaults>Default Reporting Units

With the tracking method set to "Actual work done and work remaining", you
are presented with work planned in days and the amount of effort spent can be
entered in days.  However you don't get a timephased entry table as you do
when reporting using "Hours of work done per period"

--
Did this post help you. Consider passing on the good will by making a
donation this great charity.
http://www.fundraiseonline.co.nz/TheProjectServerGuru/

http://theprojectserverguru.spaces.live.com

Thank you Paul, appreciating your helpExecutives want to see "Days" instead of

Asked By LemonWithMin
25-May-08 03:40 AM
Thank you Paul, appreciating your help

Executives want to see "Days" instead of "Hours" in the Work field for all
the available views.

I tried your suggestion but still "Hours" appear in the Work field. are you
sure this will address our requirement here?

Thank you,

No it won't.

Asked By pconroyATtheprojectserverguruDOTcoDOTnz
25-May-08 05:36 AM
No it won't.

You could however create a custom field to recalculate work to days and show
this column instead of the work column.

Paul
--
Did this post help you. Consider passing on the good will by making a
donation this great charity.
http://www.fundraiseonline.co.nz/TheProjectServerGuru/

http://theprojectserverguru.spaces.live.com
Thank you again PaulYou are right; this might be a possible workaround.
Asked By LemonWithMin
25-May-08 08:50 AM
Thank you again Paul

You are right; this might be a possible workaround. Do you know other
alternatives?
sorry no.-- Did this post help you.
Asked By pconroyATtheprojectserverguruDOTcoDOTnz
25-May-08 02:02 PM
sorry no.

--
Did this post help you. Consider passing on the good will by making a
donation this great charity.
http://www.fundraiseonline.co.nz/TheProjectServerGuru/

http://theprojectserverguru.spaces.live.com
Post Question To EggHeadCafe