Hello my friends,
I identifyed two problems on this and solved just one:
1) The values in BCWS and BCWP turned zero - still remains!
Partial solution: how I couldn?t just save the baseline, I made a copy to another blank baseline, saved the baseline 0, copied again the original baseline to 0 and cleared the created baseline. I made it by code transparently to the user. This problem remains, because I haven?t identifyed the main cause, so I can occur again.
2) Some projects were calculating the BCWP value wrong - solved!
Solution: This problem occurred because in the middle of the project I changed the aggregate calculation method from "% complete" to "% physical complete". The solution was just to reset for each task the "% physical complete" column, setting it to 0 and then to its original value.
Thanks for the answers and I still am looking for the main solution.
Regards,
Caio
E-mail: caio.pereira@gmail.com
MSN: caio.pereira@hotmail.com
Problem with BCWS and BCWP columns
14-set-09
Hello,
Some projects are losing their values in the column bcwp and bcws.
I am creating the project creating the tasks and saving the baseline, as
usually. But, some days, and maybe months later, when I reopened the project,
the bcwp and bcws values were set to 0 (zero).
The values for the baseline are still there in baseline column.
Is there a way to restore/recalculate these values in bcwp and bcws column?
Reset values (tools/tracking/set baseline - entire baseline) is not a option.
Any help will be appreciated.
Regards,
Caio
EggHeadCafe - Software Developer Portal of Choice
JavaScript Calendars
http://www.eggheadcafe.com/tutorials/aspnet/db701e2f-229f-4137-82f1-88bb49b66598/javascript-calendars.aspx