Project - Total Cost Calculation for MS Project 2007
Asked By drlabon
20-Nov-09 04:52 PM

Good Afternoon,
Here is the scenario/problem:
I have created a task (100 days duration) and assigned 2 resources to
the task at a straight time rate of 22 per hour. One resource (A) has a
max unit of 100% which is assigned at 100% the total cost according the
resource sheet is 22,000. Resource (B) is at the same pay rate, same
assignment level 100% but has a max units % of 400% (Indicating 4 group
resources assigned at 100%. The total cost according the resource sheet
still reads 22,000. How can that be?? Am I not understanding something
or am I missing a step?
Recap:
Resource A = Max Units 100% at 22 per hour straight time for 100 days =
Total cost of 22,000
Resource B = Max Units 400% at 22 per hour straight time for 100 days =
Total cost of 22,000
Why is the total cost the exact same???
thanks for any help anyone can provide!
--
drlabon
------------------------------------------------------------------------
drlabon's Profile: http://forums.techarena.in/members/156649.htm
View this thread: http://forums.techarena.in/microsoft-project/1273597.htm
http://forums.techarena.in
Microsoft Project
(1)
VBA
(1)
Database
(1)
FAQs
(1)
HiMy
(1)
Trainer
(1)
Window
(1)
Gantt
(1)
Rod Gill replied to drlabon
Max units for a Resource is purely the maximum allocation allowed before a
Resource is flagged as over allocated.
Do you mean Max units or Peak units or what? What is the Work value for
Resource B on that Task?
--
Rod Gill
Microsoft MVP for Project
Author of the only book on Project VBA, see:
http://www.projectvbabook.com
__________ Information from ESET Smart Security, version of virus signature database 4625 (20091120) __________
The message was checked by ESET Smart Security.
http://www.eset.com
drlabon replied to drlabon
I have 400% inputed into the Max Units field.
--
drlabon
------------------------------------------------------------------------
drlabon's Profile: http://forums.techarena.in/members/156649.htm
View this thread: http://forums.techarena.in/microsoft-project/1273597.htm
http://forums.techarena.in
JulieS replied to drlabon
Aren't both resources assigned at 100%? Setting the max. unit at
400% does not mean that the resource is **assigned** at 100%. View
the Gantt chart, split the screen (Window split) and view the
assignment units.
I also do not see how a resource can be assigned to a 100day duration
task at $22.00 per hour and have a cost of 22,000. Shouldn't there
be 800 hours of work (8 hours per day * 100 days) for a total cost
of $17,600? Do you have a ten hour day set up? It sounds like you
have a 10 hour day * 100 days for 1,000 hours of work for each
resource.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
Steve House replied to drlabon
A resource with a Max Units of 400% means there are 4 individuals available
for possible assignment but assigning that resource to a task at 100% does
NOT mean that all 4 individuals are working on it. Instead it means only 1
out of the 4 is assigned to the task in question, leaving the other 3 idle
and available for assignment.
--
Steve House
MS Project Trainer & Consultant
vanita replied to drlabon
Hi
My suggestion would be that when working with people view Max. units and
assignment data in numbers instead of %, then such confusions may not arise.
To change this option go to Tools > options > schedule and change the option
of 'Show assignment units as a' to decimal.
I hope it helps.
Vanita
--
Project Management consultant and trainer
vanita_ahuja@yahoo.com
Steve House replied to vanita
That's why I always describe the assignment percentage as being a rate
variable. it is not the percentage of the resource's workday or work week
that they can spend on the project or on a task as people sometimes think.
Rather, it is an indicator of the rate at which the resource converts units
of working time spent into full-time equivalent work output. "100%" means
100 percent of the time spent is converted into useful work while "50%"
means that only half of the time actually spent appears as useful man-hours
of work.
--
Steve House
MS Project Trainer & Consultant
How do we determine crew size with Microsoft Project? Project How do we determine crew size with Microsoft Project? Project Discussions Microsoft Project (1) Excel (1) VBA (1) Microsoft Project Crews (1) Database (1) Project Project (1) Physical
How do i "strikethrough" when using Microsoft Project Project How do i strike through a sentence (as you will do in a Microsoft Word Font) when using Microsoft Project? Project Discussions Microsoft Project (1) Microsoft Word (1) Project 2010 (1) VBA (1) Database (1) Strikethrough (1) Thunk
Maximum number of tasks possible in a Project Project Project Developer Discussions Microsoft Project (1) Project 2010 (1) Project 2007 (1) VBA (1) Database (1) Messemaeker (1) Promises (1) Prom (1) I once read 1 million. - - Jan
microsoft project Project what is the purpose of Microsoft Project Project Discussions Microsoft Project (1) VBA (1) Juan (1) CFAF865342AD (1) Start here: http: / / office.microsoft.com / en-us
Interfacing AJERA with Microsoft Project or Microsoft Project Serv Project I am curious if anyone has any experience interfacing AJERA database data with Microsoft Project or Microsoft Project Server 2007. I would like to develop a product that allows me to create