Project - Non Working day not showing in Gantt Chart

Asked By Cazzy123
21-Nov-09 08:44 AM
Hi I have made a copy of the standard calendar and in the copy calendar under
Change Working Time I have added a couple of Non Working days.  They show up
as an 'exeption day' in calendar here but when I look at the date in the
gantt view it is still showing as a working day.

I have checked under the Project properties that the Copy Standard calendar
is being used.

Has anyone any idea as to why it is not showing in the Gantt Chart.

Thanks
Microsoft Project
(1)
Trainer
(1)
Monday
(1)
Gantt
(1)
Basecalendar
(1)
Timescale
(1)
Day
(1)
  Steve House replied to Cazzy123
21-Nov-09 01:40 PM
The Gantt chart non-working time display can be controlled by any base
calendar you choose and is set indepedently of the Project Calendar setting.
To have your customized calendar control the non-working day display, right
mouse-click on the timescale, choose "Timescale," select the Non-Working
Time tab, and set your desired calendar as the controlling calendar from the
drop-down box.
--
Steve House
MS Project Trainer & Consultant
  Cazzy123 replied to Steve House
22-Nov-09 03:43 AM
That works a treat, thanks Steve
  Benoit Lhote replied to Steve House
20-Jan-10 06:38 AM
Thank you Steve.

It works also for me, it helps..



In fact I have a related need and a related question to solve:

- I would like to display Non-Working Time (let's say NWT) in Gantt view



a) first need, "NWT" defined in Calendar associated to current project

-> that's the aspect covered by Steve's answer -> ok, solved !



b) second need, "NWT" defined in a resource calendar; for example, let's say that "Ben" will not work on next Monday,

My context: I manage projects with several resources and it would be a help to visualize the non working time of people on same Gantt view than the overall project.

I agree that my need is not completely well formed, as I expect a mix between global info on project WITH personal info on a given person.

Your ideas are welcome....

Best Regards

Ben,
Create New Account
help
Microsoft Project 2007 and SharePoint Project I created a Project 2007 file and need to publish it to my SharePoint site so that my team can update their tasks as created in the Project file. Can any one help me with this? Project Discussions Dale A. Howard MVP VP (1) Steve House Microsoft Project Trainer Consultant Amer (1) Microsoft Project (1) Project Server (1) SharePoint (1) Project 2007 (1
How can I use calender days instead of workdays in Project Project Project Discussions Microsoft Project (1) Messemaeker (1) Trainer (1) Encompasses (1) Workdays (1) Proceeds (1) Edays (1) Days (1) Hi, First reaction: where? what for? OK there are several ways: 1.Change the project calendar by making Sat and Sun working days 2. Use "edays" for durations. HTH - - Jan De Messemaeker Microsoft Project Most Valuable Professional +32 495 300 620 For availability check: http: / / users.online.be
Setting up Microsoft Project Server Project In addition of security, what initial setup is necessary and should be considered when first implementing Microsoft Project Server for a project? Project Server Discussions Microsoft Project (1) FORTUNE (1) MVP (1) DBA (1) EE (1) DD (1) Project (1) Server
Does microsoft project 2003 appear easy to learn? Project Project Discussions Microsoft Project (1) Microsoft Word (1) Project 2007 (1) Office (1) FAQs (1) ArticleSearch (1) RichardJ (1) TechTrax (1) Hi, Trying to
unavailable features using Project Web Access Project What features of Microsoft Project aren’t available when using the Project Web Access portal to connect to Project Server? Project Server Discussions Microsoft Project (1) MVP (1) PWA (1) ABB (1) FBC (1) BA (1) AD (1) PM